Move 6 largest pieces of a used tunnel boring machine
Develop a cost-effective solution to accommodate a limited budget for moving scrap pieces
Specific factors:
Limited access to loading and offloading sites
Transportation through the busy metropolitan area (Vancouver and Burnaby)
Multiple changes in the project timeline
Accomplished tasks:
Calculated the project budget and agreed contract terms with the customer
Received permits and approvals from multiple stakeholders (independent engineers, utility companies, City of Burnaby and City of Vancouver engineering departments, public transit operator)
Managed frequent project schedule and scope changes
Coordinated the work of subcontractors (crane company, pilot car operator, outside carrier)